#1548: Automatically 'guess' the date that milestones will complete....
---------------------+------------------------------------------------------
Id: 1548 | Status: new
Component: roadmap | Modified: Fri May 13 09:35:53 2005
Severity: normal | Milestone:
Priority: normal | Version: devel
Owner: cmlenz | Reporter: scott at switzer.org
---------------------+------------------------------------------------------
On the roadmap page, a date is set which is the completion date of the
milestone. You can also 'guess' when this project will be completed,
based on the number of items in the milestone, and the average amount of
time it takes for them to complete. This can give you the estimated time
before completion.
For example, if there are 25 tickets in a milestone, and on average there
are 3 tickets closed per day, and 16 tickets have already been closed,
Trac can calculate that it will take an estimated 3 days before this
milestone is complete.
This would work perfectly for an Agile development process like Scrum,
which uses burndown charts religiously.
Thanks,
Scott Switzer
M3
--
Ticket URL: <http://projects.edgewall.com/trac/ticket/1548>